News & Events

Filter:
  • P6290507
  • P6290016 (1)
  • P6290577
  • P6291108
  • P6290600

College Gardens Construction Site Update - July 2017

Building status update for the College Gardens residential project as of 2nd July 2017:

Block 5

Superstructure 85% complete, internal finishes and first fix electrics/plumbing and carpentry progressing. Baths/showers to commence within the next 2 weeks. Kitchens to commence being fitted and scaffolding to be removed within the next 4 weeks.

Block 3

Sub structure work progressing to the basement, in particular shuttering, re-inforcement and concrete to slab/basement walls. Re-inforcement and concrete to podium level advancing well.

Block 2

Excavation complete and works advancing in basement in particular shuttering, blinding re-inforcement and concreting to walls and slab. Works to columns and perimeter walls to be advanced in the next 2-4 weeks.

Block 1

Excavation works progressing, installation of buried services, reduce level dig to be complete within the next 4 weeks.

Block 6

On schedule with structural repairs and steel frame works advancing sequentially, crack repairs and rendering advancing.

Block 4

On schedule, first floor slab complete and second floor slab works progressing. Blockwork to the 3rd floor to be complete in 4 weeks. Stairs to be installed within 2-4 weeks. First fix mechanical and electrical services to be undertaken in 2-4 weeks.

 

< Back to News list