College Gardens Construction Site Update - Apr 2019

Please read below a summary of the on-site status of the construction progress at the College Gardens development:

CAVELL HOUSE 

After the final finishing stages were completed in the autumn of 2018, we were delighted that Cavell House achieved completion on 30th November 2018 and our new residents are settling in to their new homes. 

 AUSTEN-BARTLETT HOUSE

The 45 one and two-bedroom apartments on Austen-Bartlett House’s upper ground floor, podium level and upper floors are set to achieve completion later this month. The associated basement car park, stores, communal areas, hard and soft landscaping, La Pouquelaye site entrance, access road and visitor car parking areas are also scheduled for completion at the end of April 2019. 

 The three lower ground floor apartments are scheduled to be completed at the end of May 2019. 

The teams are in place concluding some of the final works including the first and second fix electrics, plumbing and carpentry, tiling, decoration, snagging, corridors and the lift installation. 

The external on-site works include the block paving and tarmac finishes, planting and parking bays, entrance gates and barrier as well as the final snagging and inspection works