College Gardens Construction Site Update - Aug 2017

Building status update for College Gardens residential project as of 3rd August 2017:

Block 5   (D) Inglis House       (Expected completion Spring 2018)                                

Superstructure works are now concluding and include balcony 85% complete, render 90% complete (to be complete + 2 weeks) and balconies 75% complete. Internally plastering/dry lining to be complete, 2nd fix electrics, plumbing and carpentry nearing completion, kitchens fitted.  

Block 3  (C) Curie Fry House            (Expected completion Autumn 2018)                              

Sub structure works progressing to basement slab and walls in particular shuttering, concrete and reinforcement. DPC works, tanking and blockworks to First Floor advancing.  

Block 2   (B) Cavell House        (Expected completion Autumn 2018)                                 

Excavation complete and works advancing in basement in particular shuttering, blinding re-enforcement and concreting to walls and slab. Works to podium decking and formwork walls advancing in next 2 weeks. Works to perimeter walls and podium advancing in +4 weeks.

Block 1    (A) Austen-Bartlett House       (Expected completion Spring 2019)                                 

Excavation works nearing completion, works to foundations and retaining walls progressing, installation of services to complete.

Block 6    (E) Nightingale House     (Expected completion Summer 2018)                                   

Overall on programme, structural repairs to floors/walls and steel frame works advancing sequentially, works to roof advancing including fascia boards, lead work, felt and batten, wall crack repairs, window reveals damp proofing and rendering advancing. Window installation and steel frame installation in next 4 weeks.   

Block 4    (F) Garrett Anderson House       (Expected completion Spring 2018)                                

Overall on programme as at 28th July 2017. Superstructure works advancing including shuttering, re-bar and concrete to 3rd floor Blockwork to 3rd floor complete + 2 weeks. Rear retaining wall to complete in + 4 weeks. 