College Gardens construction site update - Dec 2017

Current building status of the College Gardens residential development as of 1 December 2017.

 

Block D – Inglis House

Superstructure now complete. Final fixing, floor finishes, testing and commissioning is completing. External works 25% complete.

Block E – Nightingale House

Exterior decoration and progressive scaffold removal. Demolitions to west wings. Interior fitting out is advancing including First fix electrics/plasterboard/carpentry. Window installation advancing. Basement works and lift installation advancing.

Block C – Curie House Fry

Superstructure complete, superstructure shuttering, rebar and concrete to 2nd floor complete. Blockwork and structural steelwork to roof advancing. Interior First fix electrics advancing. 

Block B – Cavell House

Sub structure complete, substructure; shuttering, rebar, concrete and blockwork complete to first floor. Second floor works advancing. 

Block A – Austen-Bartlett House

Reduce level dig/excavation complete. Blinding/shuttering/reinforcement/concreting of basement stab complete. Progressing with shuttering/reinforcement/concreting to ground floor slab.