College Gardens Construction Site Update - July 2017
Building status update for the College Gardens residential project as of 2nd July 2017:
Block 5
Superstructure 85% complete, internal finishes and first fix electrics/plumbing and carpentry progressing. Baths/showers to commence within the next 2 weeks. Kitchens to commence being fitted and scaffolding to be removed within the next 4 weeks.
Block 3
Sub structure work progressing to the basement, in particular shuttering, re-inforcement and concrete to slab/basement walls. Re-inforcement and concrete to podium level advancing well.
Block 2
Excavation complete and works advancing in basement in particular shuttering, blinding re-inforcement and concreting to walls and slab. Works to columns and perimeter walls to be advanced in the next 2-4 weeks.
Block 1
Excavation works progressing, installation of buried services, reduce level dig to be complete within the next 4 weeks.
Block 6
On schedule with structural repairs and steel frame works advancing sequentially, crack repairs and rendering advancing.
Block 4
On schedule, first floor slab complete and second floor slab works progressing. Blockwork to the 3rd floor to be complete in 4 weeks. Stairs to be installed within 2-4 weeks. First fix mechanical and electrical services to be undertaken in 2-4 weeks.