College Gardens construction site update - Mar 2018

Please see below the latest construction site update at the College Gardens development:

Inglis House

The inspections and completions/finishing of internal apartments and Inglis House has concluded. External areas including the landscaped areas such as the terraces, pathways and car parking spaces are progressing.

Nightingale House

The internal fit out of individual apartments and communal areas are advancing, this includes laying of flooring, partitioning, fixing, services installation and kitchen fitting. Plaster boarding and insulation works are taking place in certain areas.

Curie-Fry House

The structural steelwork and roof covering are complete with window installation and balcony construction advancing. Interior fit-outs of apartments are progressing with partitioning and plumbing, electrics and carpentry. Kitchen installation throughout the building.

Cavell House

Structural works are progressing including roof carcass/covering, blockwork (third floor) and window installation throughout the building.

Austen Bartlett House

Structural works are progressing including concrete, shuttering, re-bar and blockwork to first, second and third floors.

 

 