College Gardens Construction Site update - Nov 2018

Please read below a summary of the on-site status of the construction progress at the College Gardens development:

Curie-Fry House (Block C) x35 units and includes 28 Assisted purchase first-time buyer units.

Pratically completed and handed over on 12 Oct 2018.

Cavell House (Block B) x26 units

Scheduled to achieve pratical completion on 30 November 2018. Works in progress include; internal balustrading, internal finishes, kitchen installations, cleaning, snagging and inspections.

Austen Bartlett House (Block A) x48 units and includes 12 Assisted purchase first-time buyer units

Scheduled to be pratically completed for Q2 2019. Works in progress include; 1st fix electrics/plumbing, internal/external render, ceilings, plasterboard, carpentry, plastering, tiling.