College Gardens Construction Site update - October 2017

Building status update for the College Gardens residential project as of 16 October 2017.

Block D (Inglis House)

Final elements to superstructure being completed. Final fixing, floor finishes, testing and commissioning almost complete to first cycle of 5 apartments. Cycle 2 of 5 apartments final fixing, floor finishes, testing and commissioning progressing.                                                             

Block E (Nightingale House)          

Overall on programme. Dome is complete externally; external finishing/decoration works are in progress. Scaffolding beginning to be removed periodically.

Block C (Curie Fry House)                

Sub structure; virtually complete, formwork to be struck imminently. Superstructure; Rebar and Concrete to 1st floor slab complete – Blockwork 1st to 2nd floor 20% complete. 

Block B (Cavell House)                 

Sub Structure  complete. Superstructure; dpc’s to ground floor and tanking in progress. Blockwork ground to 1st floor 50% complete. 

 Block A (Austen-Bartlett House)               

Reduce level dig/excavation 10% remaining. Blinding/shuttering /re-inforcement/concreting of basement slab to be complete in 2-4 weeks. Progressing with shuttering/reinforcement to basement walls.