College Gardens construction update (31/01/2017)

We are delighted to provide you with a construction update for College Gardens

Dated 31 January 2017:

  • Works to Block 5 (Inglis House) on programme in terms of sub-structure complete and super structure elements in progress including shuttering, blockwork, tanking/dpc, Drury lane wall and drainage works.

 

  • Works to Block 4 (Garrett Anderson House) include basement structural works progressing.

 

  • Works to former College building (Block 6 Nightingale House) on programme including structural alterations, steelwork, cleaning and lintel replacement

 

Photo taken on 27 January 2017