College Gardens Construction Site update - Aug 2018

Please read the latest construction update:

A - AUSTEN-BARTLETT HOUSE

Structural works are complete, building is wind and watertight and internal trades finishings are advancing on all floors.  

C - CURIE-FRY HOUSE

The superstructure is complete and 75% of the units are approaching completion.

Works include second fix electrics/carpentry, landscape, decorations, cleaning and inspections.   

E - NIGHTINGALE HOUSE

East Wing  - Handed over on 27.07.18

West Wing – Completions commencing 10th September

Works include staircase, decorations, carpets, signage, landscape works, external areas, cleaning and inspections.   

B - CAVELL HOUSE

Structural works complete. Internal trade finishing advancing including second fix electrics, carpentry, plumbing. Also kitchen installations, tiling, cleaning, balcony finishes and inspections advancing.