News & Events

Filter:
  • C-JDC-10299
  • C-JDC-10288 (1)
  • C-JDC-10298
  • C-JDC-10301
  • C-JDC-10309

College Gardens construction site update (May 2017)

Building status update for the College Gardens project as of 1st May 2017, which is as follows;-

Block 5
Sub Structure complete, windows installation complete, building to be watertight by 15.05.17, first mechanical and electrical fix to commence by 15.05.17.

Block 3
Sub structure works progressing to basement in particular services, shuttering, reinforcement and concrete to slab and shuttering to basement walls.

Block 2
Excavation works progressing for foundations and concreting, installation of buried services.

Block 1
Excavation works progressing, installation of buried services, piling commenced on 03.05.17.

Block 6
Overall on programme, North West demolition works complete, works to lift and services riser progressing and fit out on programme.

Block 4                        
Ground floor slab completing, blockwork to first floor level progressing, retaining walls completing.

 

Photography supplied by Andy Le Gresley.

< Back to News list