College Gardens construction site update (May 2017)
Building status update for the College Gardens project as of 1st May 2017, which is as follows;-
Block 5
Sub Structure complete, windows installation complete, building to be watertight by 15.05.17, first mechanical and electrical fix to commence by 15.05.17.
Block 3
Sub structure works progressing to basement in particular services, shuttering, reinforcement and concrete to slab and shuttering to basement walls.
Block 2
Excavation works progressing for foundations and concreting, installation of buried services.
Block 1
Excavation works progressing, installation of buried services, piling commenced on 03.05.17.
Block 6
Overall on programme, North West demolition works complete, works to lift and services riser progressing and fit out on programme.
Block 4
Ground floor slab completing, blockwork to first floor level progressing, retaining walls completing.